Sponsored by:

applied bolting technology

 

Calvin Coolidge Bridge Project



Links

UMASS RTIC

PROJECT OVERVIEW

Calvin Coolidge Bridge uses Squirter DTI's -Click on link for more info.

This information Kindly Provided by University of Massachusetts-Amherst RITC Center.

The Coolidge Bridge Reconstruction Project consists of a number of improvements to improve the capacity and safety of the bridge, while maintaining and enhancing its historic character. The project is anticipated to take approximately two years, beginning July 30, 2001 and ending August 30, 2003. Update: Work began in the Summer of 2001 and is on schedule to be complete by August 30, 2003.

Planned improvements include:
  • Widening the Bridge from 3 lanes to 4 lanes, i.e., 2 travel lanes in each direction;
     
  • Replacement of the deteriorated bridge deck;
     
  • Refurbishing the historic Art Deco bridge railing and integrated light fixtures;
     
  • Cleaning and restoration of all granite facing;
     
  • Installation of a new 5-foot sidewalk on the north side of the Bridge; and
     
  • Repairing and improving the Bridge approach roadways.
  • Full reconstruction begins at the intersection of Route 9 and Damon Road in Northampton and extends eastward approximately 2,940 feet across the Connecticut River, ending just east of the Route 9/Aqua Vitae Road intersection in Hadley.

    Structural Improvements: Support for the widened roadway will come from the existing floor beams which will be lengthened by five feet on each side of the bridge to support additional stringers added along the exterior of the bridge on both sides. The existing T-beam superstructure on the Hadley and Northampton approach spans will be completely replaced with a pre-stressed concrete box beam superstructure. On the steel deck truss main spans the existing floor beams will be extended and new steel stringers will be added to the existing steel stringers. The existing concrete deck on the main spans will be replaced by a 5 inch steel grid deck, half filled with concrete.

    Approach Roadway Improvements: On the Northampton approach, the existing roadway will be widened by about 14 feet to match the proposed widening of the bridge as far as the intersection of Route 9/Damon Road. A 5-foot concrete sidewalk will be constructed along the north side of the road and the existing traffic island will be realigned to match the shifting lanes on the bridge.

    On the Hadley approach, four 12-foot wide lanes and a 5-foot sidewalk will be constructed, as well as a 12-foot wide turning lane for westbound traffic turning into Aqua Vitae Road.

    Roadway Widening: A fourth travel lane will be added to the Bridge in the Westbound direction to increase the traffic capacity of the Bridge. To accomplish the 12 foot roadway widening on the bridge, MassHighway proposes to narrow each of the massive Art Deco abutment pylons by approximately 6 feet. The narrower cavity within the reconstructed pylons will then be filled with an inert material to ensure the pylons' structural integrity.

    Pylon Modification and Rehabilitation: In consultation with the Northampton and Hadley Historical Commissions and with the Massachusetts Historical Commission, MassHighway has developed a plan to modify the Bridge's large granite pylons to accommodate the additional traffic lane.

    The portion of each pylon that faces the roadway will be dismantled while the granite facing, bronze plaques, door assemblies, lanterns and carved stone panels will be removed, cleaned, restored as needed and reinstalled on the rebuilt pylon. When the rebuilding process is complete, each pylon will be narrower, but it is intended that the long sides of the pylons with their incised lettering and bronze doors and lanterns or bronze plaques will look the same from the sidewalk and roadway and have essentially the same dimensions as they do now. On the narrowed ends of the pylons the granite facing will be modified to accommodate the narrower width. In order to maintain the existing spread of the wings of the carved corner eagles on the narrowed pylon ends, as requested by the three historical commissions, an 18-inch granite-faced, concrete addition will be anchored to the back of each pylon, faced with stepped granite coursing so that it blends as much as possible with the existing granite detail. New granite facing, where it is needed to augment the salvaged facing, will match the existing.

    In addition, all original granite facing will be cleaned and restored. Plans and special provisions for the proposed rehabilitation project call for all stonework to be done by skilled stone carving artisans experienced in masonry restoration.

    Railings: The existing 3-foot 6-inch high, welded steel Art Deco bridge railing and its integral light standard posts will be removed, cleaned and rehabilitated. The will be repainted to match the existing green color of the railing, and. If needed, any deteriorated portions of the railing will be re-fabricated to match the existing railings. Because the existing decorative railing is not crash-tested to AASHTO standards, a Type BR2 metal crash rail must be placed at curb for the length of the bridge. The crash rail is 12 inches high set on a 15-inch high concrete base.

    The existing granite-faced, paneled approach railings must be replaced as a result of the roadway widening and reconstruction of the pylons. The new concrete approach railings will be faced with new granite facing of a size and color to match, as closely as possible, the existing.

    Light Fixtures: The original Art Deco light standard posts on the Calvin Coolidge Bridge were integral to the design of the bridge railing. The existing cobra head standards will be removed and replaced with new decorative, "tear drop" style luminaries.

    Historical Marker: A Massachusetts Bay Colony Tercentenary Commission historical marker, which stands on the north side of the Hadley bridge approach will be removed, wrapped in a moisture-permeable material to deter rust, and carefully stored in the MassHighway District 2 office in Northampton during construction. At the completion of construction, the marker will be reset at a location to be agreed upon by the Hadley Historical Commission.
     

    Web-Stat hit counters

    HISTORY OF THE COOLIDGE BRIDGE

    The Calvin Coolidge Memorial Bridge (1937) is a five-span, single intersection Warren deck truss bridge with distinctive Art Deco design on its granite-faced abutment pylons. Art Deco ornamentation on the pylons includes carved eagles and incised carved lettering. The Bridge was funded under the Hayden Cartwright Act, one of the numerous Federal aid programs designed to provide construction jobs during the Depression. It was designed by W & L Engineering Co., Engineers in conjunction with Maurice A. Reidy as Consultant and Desmond and Lord as Architects. The Bridge was built by T. Stuart & Sons.

    The bridge was designed as memorial to President Calvin Coolidge (1872-1933), a long time resident and former mayor of Northampton. Coolidge was elected to the State Senate and the governorship of Massachusetts before being elected President of the United States. A bronze memorial plaque of Calvin Coolidge is mounted on the northeast and southwest pylons.

    The bridge features large, distinctive granite-faced pylons in the Art Deco style, measuring 15 by 27 feet at the base. On the northwest and southeast pylons are bronze doors that provide access to a small room reportedly used as posts for air raid wardens during World War II.

    The 3-foot, 6-inch high welded steel Art Deco bridge rail is mounted at back of sidewalk on the north side of the bridge and on the bridge parapet on the south side where there is no sidewalk. It is a weathered green color. Integral to the rail are light standard posts supporting cobra head luminares. The cobra head luminares replaced the original low-pressure sodium lamp fixtures developed by General Electric. These lamps were based on a European model and introduced to the U.S. market in 1933. However, the yellow/orange, monochromatic light produced by the luminaire ultimately became unpopular with the motoring public and use of the lamps was discontinued as color-corrected light sources became available.

    In 1987, the Massachusetts Historical Commission determined that the Calvin Coolidge Bridge was not eligible for individual listing in the National Register of Historic Places but was eligible for listing as a contributing element in the (then) pending expansion of the Hadley Center Historic District. In 1994, the Bridge was included as a contributing element to the Hadley Center Historic District.

    Project News:
    Phase II Begins at the Calvin Coolidge Bridge
    By Tim Baril
    Published By Cianbro Corporation
     
    Cianbro is rehabilitating the Calvin Coolidge Bridge in Northampton, Massachusetts.

    Along with November’s cold temperatures and snowy weather came the end of Phase I here at the Calvin Coolidge Bridge in Northampton, Massachusetts.

    Busy tying up loose ends to complete the traffic pattern for Phase II, Cianbro crews and operators did an excellent job removing and resetting the approximately 3,200 feet of concrete traffic barrier. To limit exposure to traffic, extra attention was given to safety, due to the high flow of traffic, and often times erratic driving of motorists.

    After the traffic was switched for Phase II, removal of the existing bridge rail was the first work activity along with the necessary dirt work for crane and personnel access at both approaches. (Taking every precaution as to not disturb any environmentally sensitive areas.)

    Demolition on south side of the bridge began in December. The demolition will open up the deck to allow our ironworkers access to the bridge’s infrastructure to perform the installation of the floor beam extensions, stringer replacements and steel repairs.

    While the steel crews are busy with their necessary work, civil crews will be working on the bent extensions to widen the approaches, concrete repairs and assisting in the disassembly of the two remaining granite pylons. And, Connecticut Stone returned for the disassembly and restoration of the granite pylons and the attached approach walls.

    The original contract included the removal of the 16 original bridge bearings and the installation of new seismic isolation bearings, half of these were replaced in Phase 1, and the remainder will be removed and replaced in this phase.

    The management team led by Superintendent Guy Wilson, includes Project Engineer Jason Molten, Craft Superintendent Bruce McNamara, Safety Specialist Barbie Rushford, Field Engineer Tim Baril, Field Engineer Intern Keith Locke, and Field Administrator Terra Thomas. Moving forward we are confident that the knowledge gained from Phase I will help to hasten and improve our progress and we look forward to a safe and prosperous year here at the Calvin Coolidge Bridge in the remaining two stages.

    128,577 Project Safe Hours


     
    Eagles Fly High At Calvin Coolidge Bridge

     
    The Calvin Coolidge Bridge carries busy Route 9 over the Connecticut River between Hadley and Northampton, Massachusetts.

     

    Join Cianbro Web TV Reporter Tracey Howes as she introduces the first in a series of visits with our team at the Calvin Coolidge Bridge Project in Northampton, Massachusetts, where Cianbro is rehabilitating and widening the Route 9 Bridge over the Connecticut River.

    In this visit, we'll catch up with Cianbro Superintendent Ben Wagg. Ben will tell us about the ongoing deck repairs along with the superstructure concrete work. Ben will also let us know how the Cianbro team worked diligently to save some very special eagles.


    Please click on the links below to view the story.

    View High Bandwidth Video Clip


    View Low Bandwidth
     


     

    Sponsored by:

    applied bolting technology

     

    Calvin Coolidge Bridge Project



    Links

    UMASS RTIC

    PROJECT OVERVIEW

    Calvin Coolidge Bridge uses Squirter DTI's -Click on link for more info.

    This information Kindly Provided by University of Massachusetts-Amherst RITC Center.

    The Coolidge Bridge Reconstruction Project consists of a number of improvements to improve the capacity and safety of the bridge, while maintaining and enhancing its historic character. The project is anticipated to take approximately two years, beginning July 30, 2001 and ending August 30, 2003. Update: Work began in the Summer of 2001 and is on schedule to be complete by August 30, 2003.

    Planned improvements include:
  • Widening the Bridge from 3 lanes to 4 lanes, i.e., 2 travel lanes in each direction;
     
  • Replacement of the deteriorated bridge deck;
     
  • Refurbishing the historic Art Deco bridge railing and integrated light fixtures;
     
  • Cleaning and restoration of all granite facing;
     
  • Installation of a new 5-foot sidewalk on the north side of the Bridge; and
     
  • Repairing and improving the Bridge approach roadways.
  • Full reconstruction begins at the intersection of Route 9 and Damon Road in Northampton and extends eastward approximately 2,940 feet across the Connecticut River, ending just east of the Route 9/Aqua Vitae Road intersection in Hadley.

    Structural Improvements: Support for the widened roadway will come from the existing floor beams which will be lengthened by five feet on each side of the bridge to support additional stringers added along the exterior of the bridge on both sides. The existing T-beam superstructure on the Hadley and Northampton approach spans will be completely replaced with a pre-stressed concrete box beam superstructure. On the steel deck truss main spans the existing floor beams will be extended and new steel stringers will be added to the existing steel stringers. The existing concrete deck on the main spans will be replaced by a 5 inch steel grid deck, half filled with concrete.

    Approach Roadway Improvements: On the Northampton approach, the existing roadway will be widened by about 14 feet to match the proposed widening of the bridge as far as the intersection of Route 9/Damon Road. A 5-foot concrete sidewalk will be constructed along the north side of the road and the existing traffic island will be realigned to match the shifting lanes on the bridge.

    On the Hadley approach, four 12-foot wide lanes and a 5-foot sidewalk will be constructed, as well as a 12-foot wide turning lane for westbound traffic turning into Aqua Vitae Road.

    Roadway Widening: A fourth travel lane will be added to the Bridge in the Westbound direction to increase the traffic capacity of the Bridge. To accomplish the 12 foot roadway widening on the bridge, MassHighway proposes to narrow each of the massive Art Deco abutment pylons by approximately 6 feet. The narrower cavity within the reconstructed pylons will then be filled with an inert material to ensure the pylons' structural integrity.

    Pylon Modification and Rehabilitation: In consultation with the Northampton and Hadley Historical Commissions and with the Massachusetts Historical Commission, MassHighway has developed a plan to modify the Bridge's large granite pylons to accommodate the additional traffic lane.

    The portion of each pylon that faces the roadway will be dismantled while the granite facing, bronze plaques, door assemblies, lanterns and carved stone panels will be removed, cleaned, restored as needed and reinstalled on the rebuilt pylon. When the rebuilding process is complete, each pylon will be narrower, but it is intended that the long sides of the pylons with their incised lettering and bronze doors and lanterns or bronze plaques will look the same from the sidewalk and roadway and have essentially the same dimensions as they do now. On the narrowed ends of the pylons the granite facing will be modified to accommodate the narrower width. In order to maintain the existing spread of the wings of the carved corner eagles on the narrowed pylon ends, as requested by the three historical commissions, an 18-inch granite-faced, concrete addition will be anchored to the back of each pylon, faced with stepped granite coursing so that it blends as much as possible with the existing granite detail. New granite facing, where it is needed to augment the salvaged facing, will match the existing.

    In addition, all original granite facing will be cleaned and restored. Plans and special provisions for the proposed rehabilitation project call for all stonework to be done by skilled stone carving artisans experienced in masonry restoration.

    Railings: The existing 3-foot 6-inch high, welded steel Art Deco bridge railing and its integral light standard posts will be removed, cleaned and rehabilitated. The will be repainted to match the existing green color of the railing, and. If needed, any deteriorated portions of the railing will be re-fabricated to match the existing railings. Because the existing decorative railing is not crash-tested to AASHTO standards, a Type BR2 metal crash rail must be placed at curb for the length of the bridge. The crash rail is 12 inches high set on a 15-inch high concrete base.

    The existing granite-faced, paneled approach railings must be replaced as a result of the roadway widening and reconstruction of the pylons. The new concrete approach railings will be faced with new granite facing of a size and color to match, as closely as possible, the existing.

    Light Fixtures: The original Art Deco light standard posts on the Calvin Coolidge Bridge were integral to the design of the bridge railing. The existing cobra head standards will be removed and replaced with new decorative, "tear drop" style luminaries.

    Historical Marker: A Massachusetts Bay Colony Tercentenary Commission historical marker, which stands on the north side of the Hadley bridge approach will be removed, wrapped in a moisture-permeable material to deter rust, and carefully stored in the MassHighway District 2 office in Northampton during construction. At the completion of construction, the marker will be reset at a location to be agreed upon by the Hadley Historical Commission.
     

    Web-Stat hit counters

    HISTORY OF THE COOLIDGE BRIDGE

    The Calvin Coolidge Memorial Bridge (1937) is a five-span, single intersection Warren deck truss bridge with distinctive Art Deco design on its granite-faced abutment pylons. Art Deco ornamentation on the pylons includes carved eagles and incised carved lettering. The Bridge was funded under the Hayden Cartwright Act, one of the numerous Federal aid programs designed to provide construction jobs during the Depression. It was designed by W & L Engineering Co., Engineers in conjunction with Maurice A. Reidy as Consultant and Desmond and Lord as Architects. The Bridge was built by T. Stuart & Sons.

    The bridge was designed as memorial to President Calvin Coolidge (1872-1933), a long time resident and former mayor of Northampton. Coolidge was elected to the State Senate and the governorship of Massachusetts before being elected President of the United States. A bronze memorial plaque of Calvin Coolidge is mounted on the northeast and southwest pylons.

    The bridge features large, distinctive granite-faced pylons in the Art Deco style, measuring 15 by 27 feet at the base. On the northwest and southeast pylons are bronze doors that provide access to a small room reportedly used as posts for air raid wardens during World War II.

    The 3-foot, 6-inch high welded steel Art Deco bridge rail is mounted at back of sidewalk on the north side of the bridge and on the bridge parapet on the south side where there is no sidewalk. It is a weathered green color. Integral to the rail are light standard posts supporting cobra head luminares. The cobra head luminares replaced the original low-pressure sodium lamp fixtures developed by General Electric. These lamps were based on a European model and introduced to the U.S. market in 1933. However, the yellow/orange, monochromatic light produced by the luminaire ultimately became unpopular with the motoring public and use of the lamps was discontinued as color-corrected light sources became available.

    In 1987, the Massachusetts Historical Commission determined that the Calvin Coolidge Bridge was not eligible for individual listing in the National Register of Historic Places but was eligible for listing as a contributing element in the (then) pending expansion of the Hadley Center Historic District. In 1994, the Bridge was included as a contributing element to the Hadley Center Historic District.

    Project News:
    Phase II Begins at the Calvin Coolidge Bridge
    By Tim Baril
    Published By Cianbro Corporation
     
    Cianbro is rehabilitating the Calvin Coolidge Bridge in Northampton, Massachusetts.

    Along with November’s cold temperatures and snowy weather came the end of Phase I here at the Calvin Coolidge Bridge in Northampton, Massachusetts.

    Busy tying up loose ends to complete the traffic pattern for Phase II, Cianbro crews and operators did an excellent job removing and resetting the approximately 3,200 feet of concrete traffic barrier. To limit exposure to traffic, extra attention was given to safety, due to the high flow of traffic, and often times erratic driving of motorists.

    After the traffic was switched for Phase II, removal of the existing bridge rail was the first work activity along with the necessary dirt work for crane and personnel access at both approaches. (Taking every precaution as to not disturb any environmentally sensitive areas.)

    Demolition on south side of the bridge began in December. The demolition will open up the deck to allow our ironworkers access to the bridge’s infrastructure to perform the installation of the floor beam extensions, stringer replacements and steel repairs.

    While the steel crews are busy with their necessary work, civil crews will be working on the bent extensions to widen the approaches, concrete repairs and assisting in the disassembly of the two remaining granite pylons. And, Connecticut Stone returned for the disassembly and restoration of the granite pylons and the attached approach walls.

    The original contract included the removal of the 16 original bridge bearings and the installation of new seismic isolation bearings, half of these were replaced in Phase 1, and the remainder will be removed and replaced in this phase.

    The management team led by Superintendent Guy Wilson, includes Project Engineer Jason Molten, Craft Superintendent Bruce McNamara, Safety Specialist Barbie Rushford, Field Engineer Tim Baril, Field Engineer Intern Keith Locke, and Field Administrator Terra Thomas. Moving forward we are confident that the knowledge gained from Phase I will help to hasten and improve our progress and we look forward to a safe and prosperous year here at the Calvin Coolidge Bridge in the remaining two stages.

    128,577 Project Safe Hours


     
    Eagles Fly High At Calvin Coolidge Bridge

     
    The Calvin Coolidge Bridge carries busy Route 9 over the Connecticut River between Hadley and Northampton, Massachusetts.

     

    Join Cianbro Web TV Reporter Tracey Howes as she introduces the first in a series of visits with our team at the Calvin Coolidge Bridge Project in Northampton, Massachusetts, where Cianbro is rehabilitating and widening the Route 9 Bridge over the Connecticut River.

    In this visit, we'll catch up with Cianbro Superintendent Ben Wagg. Ben will tell us about the ongoing deck repairs along with the superstructure concrete work. Ben will also let us know how the Cianbro team worked diligently to save some very special eagles.


    Please click on the links below to view the story.

    View High Bandwidth Video Clip


    View Low Bandwidth